loading

work resumes on traffic signal, street light project on deforest ave.in summit - solar street light project

by:Litel Technology     2019-08-04
work resumes on traffic signal, street light project on deforest ave.in summit  -  solar street light project
0202LLdeforest.
On January 3, 2017, the work of the Summit's Traffic Signal and Street Lamp Replacement Project on Deforest Avenue resumed, and staff members have made significant progress in the past four weeks. (
Provided by Amy Keynes)
On January 3, 2017, the traffic lights and street lamp replacement project on the summit's De Forrest Avenue resumed, and staff made significant progress in the past four weeks.
Signal and street lights will continue to be installed and activated in the next six weeks.
The new signal will include pedestrian buttons and meet all the Americans with Disabilities Act(ADA)standards.
From mid to late April, the contractor will complete the remaining concrete works on the sidewalk and arrange for the grinding and paving of the Forest Avenue between Maple Street and Norwood Avenue.
Then Lane division and parking space drawing will be carried out immediately.
The crosswalk will be installed in late May.
The project was submitted by Amy Keynes for the summit.
Custom message
Chat Online 编辑模式下无法使用
Leave Your Message inputting...